How long the solar grant takes
Every wait SEAI publishes, in the order they come.
Free, no obligation. One local SEAI-registered installer prices it, not five.
- €1,400SEAI grant for 2kWp of panels
- €2,400most you can get, with a battery
- 0% VATon solar panels for homes
Allow two to three months from signing. The grant offer comes first and is valid for 8 months. The installer's application to ESB Networks takes at least 4 weeks (20 working days). SEAI asks you to allow up to 6 weeks for payment after the paperwork, longer if it inspects.
The waits, in order
Sign with an installer
Agree the contract. Don't let them start.
Grant offer
Apply to SEAI. The offer is valid for 8 months.
ESB Networks
The installer applies to ESB Networks before the install: at least 4 weeks, 20 working days.
Panels go up
Usually a day on a house. You pay the installer.
Post-works BER
Required, and included in the grant.
SEAI pays
Once the installer sends the evidence. Longer if SEAI inspects.
Questions people ask
Why does ESB Networks need to know?
Panels connect to the grid through your meter. The installer notifies ESB Networks before the install.
Can it be faster?
The ESB wait is at least 4 weeks, so book the installer early.
Your solar grant in 3 taps
Tap your home, the size of system and whether you want a battery. Your SEAI grant and a cost after the grant show as you go. Then, if you want a price, leave your number and one SEAI-registered solar installer who covers your area rings you.